Brighton Marina to Shoreham Flood Scheme Moves to £13.5m Final Phase

Cabinet approved procurement for Phase 3 of the sea defence scheme and cut the council’s borrowing from £11.0m to £4.5m after Environment Agency funding rose to £25.9m.

Shoreham Harbour entrance, where Phase 3 of the Brighton Marina to River Adur scheme is focused
Shoreham Harbour entrance. Photo: Paul Gillett, CC BY-SA 2.0, via Geograph.

Brighton and Hove City Council's Cabinet has approved an open procurement for the final phase of the Brighton Marina to River Adur flood and coastal erosion scheme, with a construction contract estimated at about £13.5m. The Cabinet report says the council's own borrowing for the scheme falls from £11.0m to £4.5m after bigger government funding.

What Phase 3 covers

The report says Phase 3 is mainly within Shoreham Port and the Adur and Worthing area, covering Areas 2A and 2B. The works include sea wall repairs, new rock revetments and reinstated public access routes. It says they protect nationally significant port infrastructure, transport links, utilities, employment land and surrounding communities. Phase 2, at Kings Esplanade and Southwick Beach, is expected to complete in 2026, and the scheme runs to March 2028. The report gives no specific Phase 3 construction dates.

Funding

The report puts the total scheme cost at £36.5m. It lists £25.9m from the Environment Agency and Defra Flood Defence Grant in Aid, up from £14.0m, £6.1m from external contributions including Shoreham Port Authority, subject to funding agreements and final costs, and £4.5m of council borrowing. The estimated financing cost of the £4.5m is £0.370m, at 6.56% over 25 years. The report includes £1.5m of contingency, about 10% of the remaining costs.

Cabinet also approved a £9.8m increase to the capital budget, funded by the grant and external contributions, and confirmed the council as lead authority, with the Corporate Director for City Operations authorised to evaluate tenders and award the contract.

Decision

The council's decision record shows the recommendations were approved on 12 November 2026 and published on 13 November, subject to call-in until 20 November. The full papers are on the Cabinet meeting page.