Demolition and enabling works at the King Alfred site on the Hove seafront are expected to finish by the end of February 2027, with construction of the new leisure centre starting straight after and completion expected in autumn 2028, the council has said.
The timetable was given by Councillor Alan Robins, Cabinet Member for Sports, Recreation and Libraries, in a written answer to Councillor Sykes for the full council meeting on Thursday 26 November.
"Based on the current programme of works, we expect the demolition and other enabling works to complete by the end of February 2027. Construction of the new facility will begin immediately thereafter, with expected completion in autumn 2028."

The final price is still not agreed
The council has not yet given a final cost. Councillor Robins said the council is working with its professional team and main contractors to agree final delivery costs, based on detailed pricing of individual work packages from Willmott Dixon's supply chain.
That final cost will form the basis of a delivery management agreement with Alliance Leisure, and will be set out in a paper to Cabinet in January 2027, where Cabinet will be asked to agree to go ahead with the project at that price.
In a separate written question, Councillor De Oliveira pointed out that the indicative budget has already risen from about £47 million to £65 million and asked whether an independent financial audit and updated risk assessment would be published before any further major contracts are signed. The written answer did not commit to an independent audit. Councillor Robins said the September 2025 Cabinet paper set out why the £65 million budget was needed: a much larger facility than the July 2024 outline, plus extensive public realm work to complement Hove Beach Park and other seafront schemes.
"The final agreed delivery cost for the new facility, along with associated borrowing costs, will be set out in the paper to be presented to Cabinet in January 2027."
He added that the updated business case showed the bigger centre is expected to bring in significantly more revenue than the 2024 plan, which would reduce the net annual borrowing cost to the council.

Withdean pool costs blamed on the Middle East conflict
Councillor West asked why the administration had been "caught on the hop" again, after the Withdean swimming pool, which was given a £6.8 million budget in December 2025, needed more money. Cabinet is due to consider a bigger Withdean budget on 10 December, as we reported in October.
Councillor Robins said the conflict in the Middle East had hit capital projects "beyond what could reasonably have been forecast". He said higher oil prices had pushed up the cost of delivering materials and running plant, that steel had risen because of US tariffs and retaliatory tariffs, and that higher interest rates had increased the cost of borrowing as well as the cost of building.
What happens next
- End of February 2027: demolition and enabling works due to finish.
- January 2027: Cabinet paper with the final delivery cost and borrowing costs.
- Straight after demolition: construction of the new centre begins.
- Autumn 2028: expected completion.
How ImJustBrighton reported this: this article is based on the written answers councillors received for the full council meeting on Thursday 26 November 2026, published by Brighton & Hove City Council in Addendum 2, Member Written Questions with Responses on the meeting page. Quotes are taken word for word from that document. If you have more information, email info@imjustbrighton.co.uk.