Monday, 16 November 2026
Housing

Brighton Council Housing: Eight Large Panel System Blocks Face Demolition

Cabinet approved revised rehousing and lettings policies and £1.46m more for the programme covering St James’s House, Nettleton Court, Dudeney Lodge and five other blocks.

Nettleton Court and Dudeney Lodge housing blocks on Upper Hollingdean Road, Brighton
Nettleton Court and Dudeney Lodge, Hollingdean. Photo: Hassocks5489, CC0, via Wikimedia Commons.

Brighton and Hove City Council plans to demolish and redevelop eight Large Panel System (LPS) housing blocks, and its Cabinet on 12 November 2026 approved amendments to its rehousing and lettings policies and extra funding for the programme. The Cabinet report says Initial Demolition Notices were served on secure tenants of the eight blocks on 8 October 2026.

The eight blocks

The blocks named in the report are St James's House, Nettleton Court, Dudeney Lodge, Falcon Court, Heron Court, Kestrel Court, Kingfisher Court and Swallow Court. The report also covers three redevelopment areas and a proposed extension of the Nettleton Court and Dudeney Lodge site in Hollingdean. It does not state a total number of homes.

What tenants and leaseholders are told

New secure tenancy lettings in the eight blocks have been suspended, and empty homes in the blocks are being used temporarily as temporary accommodation, with decisions on when that stops delegated to officers. The Initial Demolition Notices are valid for up to seven years. The amended rehousing and lettings policies change the term "Right to Return" to "Interest in Returning". Cabinet delegated officers to draw up a policy for secure tenants who want to return, and that policy has to come back to a future Cabinet for approval. Residents in temporary accommodation will not be offered the ability to return. Cabinet also delegated a bespoke leaseholder assistance offer for exceptional cases. The report says one live Right to Buy application was suspended when the notices were served, and that the tenant has three months to submit evidence of their reasonable expenses. It also notes the intended permanent closure of the Chapel Street car park, which has been closed since 14 July 2024, subject to a Traffic Regulation Order.

Cost

Cabinet approved an additional £1.46m of Housing Revenue Account capital, covering staffing, land assembly, rehousing costs, legal costs and an independent tenant and leaseholder adviser. The report also sets out a £0.1m leaseholder assistance budget and £250,000 of additional LPS staffing. It says the three sites will not achieve break-even for the Housing Revenue Account, with viability figures to follow in a further Cabinet report on delivery routes in 2027.

Decision

The council's decision record shows the recommendations were approved on 12 November 2026 and published on 13 November, subject to call-in until 20 November. A related item on the same subject was taken as exempt business, and its report is not public. The full papers are on the Cabinet meeting page.