Royal Pavilion Gardens Restoration: Budget Rises £1.6m to £8.038m as Cabinet Approves Contract

Domes and minarets of Brighton's Royal Pavilion rising above garden trees and a lamp post in the Royal Pavilion Garden

The Royal Pavilion seen through the garden (Photo: Kailash Reddy KU via Unsplash)


Brighton and Hove City Council logo

Brighton & Hove City Council’s Cabinet has approved a £1.6m increase to the budget for restoring the Royal Pavilion Garden, taking the total to £8.038m, and has given officers the authority to appoint a main contractor. The council’s published decision list shows both recommendations were approved at the meeting on 15 October 2026.

The council says it is not putting in any more of its own money. The extra cost is to be covered by National Lottery Heritage Fund grant, a Historic England grant that has not yet been confirmed, and donations raised by the Royal Pavilion and Museums Trust. The report expects work to start on 9 November 2026 and finish in November 2027.

£8.038m
revised total budget
£1.6m
increase approved
£0.750m
total council contribution, no new money asked for
9 Nov
expected start of work

Source: Brighton & Hove City Council, Cabinet decision list, 15 October 2026


What Cabinet agreed

Budget increase
Agreed a £1.600m increase funded by National Lottery Heritage Fund money, a Historic England grant and Royal Pavilion and Museums Trust (RPMT) donations. That takes the total project to £8.038m.
Main contractor
Gave the Corporate Director, City Operations authority, in consultation with the Cabinet Member for Economy, Culture, Heritage and Tourism, to appoint a main contractor for the works within the project cost plan.
The condition
The contract depends on approval of a further £0.500m from Historic England. The report says that decision was awaited.
Call-in
The decision is a key decision and can be called in until 23 October 2026. The council’s decision page showed no call-ins when we checked.

Where the £8.038m comes from

Graphic showing the funding for the Royal Pavilion Garden restoration: National Lottery Heritage Fund 5.346 million pounds, Royal Pavilion and Museums Trust and other external 1.110 million, other public sector grants 0.832 million and the council 0.750 million, with 6.987 million secured and 1.051 million still to secure
The funding for the £8.038m budget (Graphic: ImJustBrighton, from the Cabinet report)

The report says £6.987m of the budget is secured and £1.051m is still to be secured. The council’s own contribution is £0.750m: £0.440m borrowed and £0.310m from capital receipts. Interest on the borrowing is estimated at about £46,000 a year, based on rates on 2 October 2026.

The £1.6m increase is broken down in the report as £0.550m of secured National Lottery Heritage Fund grant, a £0.500m Historic England grant application, and £0.550m of Trust donations that have not yet been secured. The Trust says its fundraising is on track. The council has also applied to Arts Council England for £0.085m.

The garden’s main funder is the National Lottery Heritage Fund, which awarded £4,369,755 in January 2024, according to Brighton & Hove Museums. The Wolfson Foundation announced a further £100,000 in January 2026, according to Brighton Journal.


Why the cost has gone up

Graphic showing how the Royal Pavilion Garden project cost moved from 6.264 million pounds in August 2023 to 8.228 million in December 2025, 7.139 million in February 2026 and an 8.038 million budget in October 2026
How the project cost moved (Graphic: ImJustBrighton, from the Cabinet report)

The report blames the knock-on effects of the Covid-19 pandemic, planning delays, construction inflation, higher material costs and extra professional fees. In August 2023 the estimated total was £6.264m. By detailed design in December 2025 it had risen to £8.228m. A review of the design and delivery approach brought the forecast down to £7.139m by February 2026.

Then came the tender. The council ran a two-stage competition. Fourteen firms expressed an interest, four were shortlisted and two submitted tenders. The report says that reflects market conditions and contractor capacity, not a problem with the process. Blakedown Landscapes was named the preferred contractor as the most economically advantageous bid.

After negotiation and value engineering, the proposed contract sum is £5.174m. The tender still came in £1.476m above the funding that had been awarded and planned. The National Lottery Heritage Fund has since awarded another £0.976m, which cut most of the gap. The £8.038m budget includes contingency of 12.5% on works and 7.5% on other costs.


What the restoration will deliver

The restoration covers the Grade II listed garden beside the Royal Pavilion. According to the council and Brighton & Hove Museums, the works include:

Regency planting
Restoring the planting design from the original plans made for George IV, with drought-resistant planting and more efficient irrigation.
Trees and wildlife
Protecting the roots of the heritage elms and supporting local biodiversity.
Railings and structures
Reinstating the historic boundary railings, based on the original 19th century designs, and repairing listed structures including Grade II listed lampposts.
Toilets
New public toilets, including a free Changing Places toilet accessed with a RADAR key.
Access and learning
Wider paths with better drainage, benches, an outdoor learning space and new signs and online information about the garden’s history.

The council says refurbishing the toilets, which will be leased to the Trust together with a new concession, should cut its running costs by about £24,000 a year. Operating costs were £91,000 in 2025, including extra maintenance and security.


Why the garden is on the Heritage at Risk Register

Historic England added the garden to its Heritage at Risk Register in 2017. Brighton and Hove News reported in 2019 that the reasons included heavy visitor use, erosion and declining historic character. Brighton & Hove Museums says John Nash designed the garden in the 1820s for King George IV and calls it a rare Regency Picturesque landscape in a precarious state.

The council says the main aim of the project is to get the garden off the register. The land is leased and managed by the Trust, and the council is the freeholder. Planning permission was granted in 2024.


Antisocial behaviour and the City Safe Zone

The report says the garden has considerable levels of antisocial behaviour, particularly in the early hours. A City Safe Zone scheme led by council officers, with National Lottery Heritage Fund support, is being developed for the garden and New Road.

The plans include visible safety marshals during higher-risk periods, outreach and support for vulnerable people, and work with local venues to improve night-time safety. Public Health has committed £50,000 to the pilot, with £35,000 of match funding from city stakeholders. The council hopes the model could be used in other parts of the city.


What if the money does not arrive

The report says officers have prepared a list of work packages that could be dropped if the £1.051m is not secured. It does not publish the list. The council says it would protect the purposes the Lottery grant requires and keep the project inside the funding it has.

If costs go over the contingency, the report says any remaining overspend would be shared equally between the council and the Trust under a Collaboration Agreement signed in September 2026. It also warns that delays could mean more inflation, extra fees and changes to the order of seasonal planting.


The ice rink

The report says the project team tried to find a way for the Royal Pavilion Ice Rink to return to its usual site this winter, but work will be happening there all winter and delaying the start would carry significant cost and funding problems. We reported on the council’s plan to bring the rink back in 2027 at the Old Steine in our article on the ice rink moving to the Old Steine.


Questions councillors submitted

Four councillors submitted written questions on the garden for the meeting, according to the council papers. The papers do not include the answers.

Councillor Meadows
Asked why this is a paper for decision if the project is not council funded, and whether it should just be for noting.
Councillor McNair
Asked whether the ice rink will return to the Royal Pavilion site in 2027/28.
Councillor Mcleay
Asked whether there are any plans for a public ice rink elsewhere in Brighton and Hove this winter, and if so where.
Councillor Sykes
Asked for the status of a long-running proposal for a sculpture in the garden commemorating Hindu, Muslim and Sikh soldiers who served in the First World War, which the recent Heritage Task and Finish Group recommended for consideration.

Royal Pavilion Gardens restoration: your questions answered

How much will the Royal Pavilion Garden restoration cost?

Cabinet approved a revised total budget of £8.038m on 15 October 2026, up £1.6m. The proposed contract with the builder is £5.174m.

Who is paying for it?

The National Lottery Heritage Fund is the biggest funder at £5.346m. The rest comes from Trust fundraising and other external contributions, other public sector grants and the council’s £0.750m.

Is the council putting in more money?

No. The report says no additional direct council funding is requested.

Who will do the work?

Blakedown Landscapes was named the preferred contractor after a competitive tender, subject to the funding and contract being finalised.

When will work start and finish?

The report expects work to start on 9 November 2026 and finish in November 2027.

Will the garden close during the works?

The report does not say whether the garden will close or which parts will be fenced off. We will update this when the council or Brighton & Hove Museums confirms.

Why is the garden on the Heritage at Risk Register?

Historic England added it in 2017. The project aims to restore it so it can come off the register.

What is a Changing Places toilet?

It is a larger accessible toilet with extra equipment for people who cannot use a standard accessible toilet. The council says the one in the garden will be free to use with a RADAR key.

Will the ice rink come back to the Royal Pavilion?

Not this winter. The council says it plans to bring the rink back in 2027 at the Old Steine.


What we still do not know

The papers do not say whether Historic England has approved the £0.5m, whether the garden will close during the works, or which work packages would be cut if funding falls short. They also do not say how the council will answer the councillors’ questions. We have not found a public announcement of the Historic England decision.


What happens next

2017
Historic England places the garden on its Heritage at Risk Register.
Jan 2024
The National Lottery Heritage Fund awards £4,369,755.
7 Aug 2024
The council’s Planning Committee approves the project, according to Brighton & Hove Museums.
14 Sep 2026
Applications for extra funding submitted, according to the report.
15 Oct 2026
Cabinet approves the budget increase and the contract authority.
23 Oct 2026
Call-in deadline on the decision.
9 Nov 2026
Estimated start of work.
Nov 2027
Estimated completion.

The report’s own programme puts contract signing on 22 October 2026. More is under Brighton and Hove City Council, heritage, Royal Pavilion Gardens and cabinet decision on ImJustBrighton.

Sources

Read more from ImJustBrighton

Brighton Ice Rink 2026: No Rink This Winter, New Old Steine Home Planned for 2027

Brighton Council Bans Gambling and Fossil Fuel Adverts on Its Advertising Sites

Black Rock Brighton: Cabinet Approves Preferred Bidder for Temporary Seafront Use

Next
Next

Brighton Council Bans Gambling and Fossil Fuel Adverts on Its Advertising Sites